Skip to main content
Design-build

Allowances

Put an allowance on the estimate for something you’ll choose later, pick against it, and settle the difference.

Written By Julia M.

Overview

Put an allowance on the estimate for something you will choose later, like a lobby chandelier.

Watch it: the Finances lesson in Campus, step 8, “Design-build”, chapter 5, “Allowances” (starts at 1:29).

Steps

  1. In a section, click Add allowance, name it and set the amount.

An allowance for the lobby chandelier
  1. When it is time to choose, click Pick products on the allowance. Pick from the project’s Library, and see how far over or under you are.

  2. Click Save the picks.

Picking for the allowance: $10,950 picked against $9,100
  1. Settle it with a change order for the difference.

The change order that settles the allowance